If an off-plan home bought in Turkey is not delivered, the buyer can claim compensation for the delay together with delivery, or withdraw from the contract and claim a refund of the price. In a pre-paid housing sale, the delivery period cannot exceed 48 months from the date of the contract, and no deduction can be made from a buyer who withdraws because of the seller's default. Before choosing a route, it must be established whether the contract was made before a notary, what the delivery date is, in which currency payment was made and whether the buyer counts as a consumer.
If an off-plan home is not delivered, when is the developer in default?
For an off-plan home, if the contract states a fixed delivery day, the developer is in default when that day passes, without any need for a further notice (Turkish Code of Obligations No. 6098, Art. 117/2). If the delivery day is not fixed, the buyer's notice is required for default. Default means that the developer has not performed its delivery obligation on time, and it is the starting point for all of the buyer's rights.
A notice is the buyer's statement calling on the developer to perform its delivery obligation; to prove the date conclusively, sending it through a notary is the safe route. A developer in default can be given a reasonable period to perform. Where giving a period would be pointless, for example if construction has in fact stopped, this is not necessary.
If the price of a residential property is paid in advance or in instalments before delivery, the sale is a pre-paid housing sale regulated by the Consumer Protection Law No. 6502. The document signed by the parties is a pre-paid housing sales contract. Most purchases popularly called "projeden ev" (a home from the project), "topraktan ev" (a home from the ground) or "maketten satış" (a sale from the model) fall within this scope. A foreigner's property purchase in Turkey is also subject to the pre-paid housing rules if it meets these conditions; the buyer's nationality does not change the outcome.
This article explains the buyer's rights when the developer does not deliver the home. A buyer's own decision to withdraw from a sale and the refund of a deposit, and construction contract disputes between the landowner and the contractor, are separate topics.
Do extension and force majeure clauses in the contract extend the delivery date?
Yes, as a rule an extension clause in the contract extends the delivery date; however, in a pre-paid housing sale the total period still cannot exceed 48 months, or, as a rule, 36 months for contracts made before 1 October 2022. In a 2023 decision, the 3rd Civil Chamber of the Court of Cassation held a 9-month extension granted to the seller to be binding under the contract and calculated the delay from the end of that period. However, the Court of Cassation has held certain clauses that bind the buyer to an additional waiting period during which no compensation can be claimed to be unfair terms.
A force majeure clause, on the other hand, does not create an extension by itself. The developer must show that an event such as an economic crisis or a pandemic actually prevented delivery and that it complied with the notification condition in the contract. In a 2025 decision, the Court of Cassation upheld a decision that rejected a force majeure defence because the stoppage of construction had not been notified to the buyer in writing. If the delivery date passed before the pandemic, the pandemic does not explain the delay, since it arose later.

The buyer's legal routes when a home is not delivered
When a home is not delivered, the buyer has two main routes: to keep the contract and claim the home and compensation for the delay, or to withdraw from the contract and recover the price paid.
The buyer can also immediately state that he or she no longer wants delivery of the home and claim the market value of the home as compensation; for homes whose value has increased, this route gives a different result from a refund. If the contract was not made before a notary or the project has been left unfinished, supplementary routes also come into question. In construction and delivery disputes, the right route depends on the form of the contract and the method of payment.
The table below shows what each route provides (Law No. 6502 and Law No. 6098; checked in November 2026).
| Route | What is claimed | Result |
|---|---|---|
| Keeping the contract | Delivery of the home and compensation for the delay or rent loss | The contract continues; the delay period is compensated |
| Withdrawing from the contract | Refund of the price paid and reliance damages | The contract ends; the price must be refunded within 180 days at the latest |
| Compensation instead of performance | The market value of the home | The home is not claimed; the value of the home is paid as compensation, taking any unpaid price into account |
| Refund under a contract not made before a notary | Refund of payments under the rules of unjust enrichment | The seller cannot rely on invalidity against the buyer |
| Claiming under the security | Building completion insurance or other security | The guarantee, insurance or security operates according to its own terms |
A buyer who withdraws from the contract because of the seller's default cannot be asked for the compensation of up to 8 percent that the law provides for withdrawal without reason.
Waiting for the home and withdrawing from the contract cannot both be used for the same delay. A buyer who withdraws from the contract can no longer claim rent loss as if the contract were continuing; the choice should therefore be made after doing the calculations.
Which facts are decisive in an off-plan home dispute?
In an off-plan home dispute, the route is determined by the form of the contract, the nature of the delivery date and the buyer's method of payment. The information "The developer is not delivering the home" does not, on its own, show which claim is more beneficial. The decisive facts are:
- whether the contract was drawn up as a notarial deed,
- the date of the contract and whether there is a fixed delivery day,
- extension, force majeure and penalty clauses,
- whether payment was in Turkish lira or in foreign currency,
- whether a mortgage loan or linked credit was used,
- whether the buyer bought a single home or a large number of flats,
- whether the construction servitude (pre-completion unit title) has been registered in the buyer's name,
- whether the developer is in concordat or bankruptcy proceedings.
Of the buyers of two flats not delivered on the same date, one may prefer to wait for the home and claim rent loss, and the other to withdraw from the contract. For a buyer who paid in dollars and does not live in Turkey, a refund may make more sense; for a buyer renting a home in Turkey, rent loss may.

The 48-month limit for pre-paid housing: when does 36 months apply?
In a pre-paid housing sale, the maximum delivery period is 48 months for contracts concluded from 1 October 2022. The law sets this limit expressly: "In any case, this period cannot exceed forty-eight months from the date of the contract." (translated from the official Turkish text) (Law No. 6502, Art. 44/1)
This limit was introduced by Law No. 7392 and entered into force on 1 October 2022; the previous maximum was 36 months. Under the transitional provision added to the law, earlier transactions are, as a rule, governed by the provision in force on the date they were made. For contracts signed before 1 October 2022, the 36-month limit is therefore, as a rule, applied.
In a pre-paid housing sale, there is no statutory penalty-free grace period for delay; the limit is the date in the contract and 48 months at the latest.
48 months is not a waiting period. If the contract states an earlier date, the developer is in default on that date and the buyer's rights begin from that day.
Is a foreigner who buys for investment or lives abroad considered a consumer?
Yes, a foreigner who buys a single home for himself or herself or for the family, or to use in the future, is as a rule a consumer, even if he or she lives abroad. Consumer status does not depend on nationality; what is decisive is whether the purchase was made for commercial or professional purposes.
One of the defences sellers rely on is that the foreign buyer "bought the flat for investment". In a 2026 decision of the Court of Cassation, a buyer living in the US who bought a single flat was considered a consumer despite this defence, and the case was heard by the consumer court.
A person who clearly buys a large number of flats for investment, however, may not be considered a consumer. In such files, the Court of Cassation has held the general court, not the consumer court, to be competent. Whether or not the buyer is a consumer determines whether the protections for pre-paid housing and the corresponding forum apply.
Can a buyer who chooses to wait for the home claim rent loss and compensation for the delay?
Yes, a buyer who chooses to wait for the home can claim, together with delivery, the damage suffered because of the delay. In the practice of the Court of Cassation, this damage can be calculated as rent loss: the comparable rent that the home could have earned during the delay period is taken as the basis.
The Court of Cassation considers it correct to award rent loss for the period between the delivery date in the contract and the actual delivery date. The calculation is made by a court expert using comparable rents in the area. The longer the delay, the greater the rent loss; the delivery date and the actual day of delivery should therefore be shown with documents.
If the contract states a fixed monthly late-delivery amount, that clause may be a penalty clause and directly affects the claim for rent loss.
Can a late-delivery penalty and rent loss be claimed together?
No, unless the contract provides otherwise, a late-delivery penalty and rent loss cannot be claimed together for the same delay. The 3rd Civil Chamber of the Court of Cassation clearly laid down this rule in its decision of 4 April 2023 (E. 2022/3824, K. 2023/962). According to the decision, "compensation for rent loss and the penalty attached to performance agreed in the contract cannot both be claimed together." (translated from the official Turkish text)
In the same decision, the contract provided for compensation of 2 per thousand of the sale price for each month of delay. The 3rd Civil Chamber of the Court of Cassation ruled that, because the rent loss was higher, the buyer had to be treated as having claimed the higher rent loss.
Unless the contract provides otherwise, a late-delivery penalty and rent loss cannot be claimed together; damage exceeding the penalty can be claimed only if the developer's fault is proven.
When and how much does a buyer who withdraws from the contract get back?
A buyer who withdraws from the contract because of the seller's default gets back the full price paid, without deductions, within 180 days at the latest from the notice of withdrawal. The law states that in this situation the seller cannot claim any amount: "If the seller does not perform its obligations at all or properly, it cannot claim any amount from the consumer." (translated from the official Turkish text)
The refund period starts from the date on which the notice reaches the seller (Law No. 6502, Art. 45/3). The Regulation on Pre-Paid Housing Sales provides that the notice of withdrawal can be made through a notary; a notice through a notary shows the date of receipt conclusively.
In its decision of 13 December 2023 (E. 2023/1972, K. 2023/3711), the 3rd Civil Chamber of the Court of Cassation did not accept a 2 percent deduction by a seller that had failed to deliver on time. The decision upheld the order to refund the amount deducted, the notary costs and the buyer's reliance damages.
Can a price paid in dollars be recovered in dollars? What did the Court of Cassation say in 2026?
Yes, if the price was validly agreed and paid in a foreign currency, the buyer can claim the refund in the same currency; however, this result depends on the facts of the file. The decision of the 3rd Civil Chamber of the Court of Cassation of 21 January 2026 (E. 2025/3057, K. 2026/271) showed this in the file of a foreign buyer.
The buyer, who lived in the US state of Texas, bought a flat in a project under construction in Istanbul through a promise-to-sell agreement signed before a notary on 7 September 2017. He paid 214,000 US dollars on the same day. The flat was due to be delivered on 31 December 2018, but it was not delivered.
The seller argued that the buyer had to deposit security because he was a foreigner, that he was not a consumer because he had bought for investment, and that the economic crisis and the pandemic were force majeure. It also argued that the right of withdrawal had been exercised late and that the buyer had benefited from the rise in the exchange rate.
The Bakırköy 11th Consumer Court ordered the refund of 214,000 US dollars with the highest interest rate applied to dollar deposits. The regional appeal court based the refund of the foreign currency in kind on the Turkish Code of Obligations. The Court of Cassation, noting that the flat had not been delivered on time, unanimously upheld the decision.
The validity of payment in foreign currency is assessed separately. Decree No. 32 on the Protection of the Value of the Turkish Currency has imposed a prohibition since 13 September 2018. Persons resident in Turkey cannot agree the price in foreign currency in real estate sales between themselves, except in cases determined by the Ministry.
According to the Ministry's communiqué, buyers who are not Turkish citizens and who are resident in Turkey are among these exceptions. The situation of a buyer resident abroad may fall outside the prohibition; residence is assessed separately according to the definition in the Decree.
If the promise to sell was not made before a notary, can the money paid be recovered?
Yes, in a pre-paid housing sale, the buyer can claim back the money paid even if the promise to sell was not made before a notary. The law requires the promise to sell to be drawn up as a notarial deed; however, "the seller cannot later rely on the invalidity of the contract to the detriment of the consumer" (translated from the official Turkish text) (Law No. 6502, Art. 41/1).
This form rule turns the consequences of a contract signed in a sales office in the buyer's favour. The seller cannot keep the payment by relying on the notarial form that it did not arrange itself. In a 2022 decision, the Court of Cassation stated that the invalidity of such a contract must be based on Law No. 6502, not on the general provisions.
The seller's invalidity defence does not, on its own, block other claims under a contract not made before a notary either. In a 2025 decision, the Court of Cassation upheld a decision ordering payment of the market value of the flat to the buyer, because the flat sold under a contract not made before a notary had been transferred to a third party.
The risks of a promise-to-sell agreement before signing and an annotation on the title deed are a separate topic.
How do building completion insurance and security protect the buyer if the project is left unfinished?
In pre-paid housing projects with 30 or more homes, the seller must take out building completion insurance or provide another form of security before starting sales. The Regulation on Pre-Paid Housing Sales lists a bank letter of guarantee, a progress payment system and linked credit as alternatives to insurance.
Building completion insurance and security are among the buyer's main protections when the developer's financial situation deteriorates. The law expressly guarantees that the insurance indemnity and security are kept separate from other creditors (Law No. 6502, Art. 42/2).
The building completion insurance indemnity does not form part of the bankruptcy or liquidation estate and cannot be attached.
Which guarantee exists can be seen from the contract and the pre-contract information form. Under the law, the pre-contract information form is the document that must be given to the buyer at least 1 day before the contract. For projects with fewer than 30 homes, there is no security requirement; the buyer's protection is limited to the contract, the land registry record and the seller's assets.
What happens to the buyer if the developer files for concordat or goes bankrupt?
If the developer is granted a definitive moratorium for concordat, the buyer cannot start enforcement proceedings against the developer during this period; proceedings already started are suspended. Concordat is protection that the developer requests from the court to restructure its debts; it is not bankruptcy. Interim injunctions and precautionary attachment orders are not enforced either (Enforcement and Bankruptcy Law No. 2004, Art. 294).
Because a claim for delivery is not a monetary claim, the buyer converts it into money of equal value and notifies it to the concordat commissioner. With the commissioner's approval, the debtor developer can undertake to deliver the home in kind. Interest on claims not secured by a pledge also, as a rule, stops running from the date of the definitive moratorium.
During concordat proceedings, building completion insurance or a letter of guarantee can therefore be direct protection for the buyer. If the construction servitude (pre-completion unit title) has been registered in the buyer's name, the buyer's position may be further strengthened.
If the developer goes bankrupt, the buyer notifies the refund claim to the bankruptcy estate and the claim is paid according to the ranking table. The building completion insurance indemnity and security, however, remain outside this estate.
Delayed delivery: consumer arbitration committee, consumer court and mediation
In a dispute arising from delayed delivery, in 2026 claims worth less than 186,000 TL go to the consumer arbitration committee, and claims above this limit go to the consumer court. The limit was set by the Ministry of Trade's communiqué published in the Official Gazette of 23 December 2025.
Most pre-paid housing disputes exceed this limit and are heard by the consumer court. Before filing a lawsuit in the consumer court, applying to a mediator is a precondition for the lawsuit. However, disputes that qualify as consumer transactions and arise from rights in rem over the property are outside this requirement (Law No. 6502, Art. 73/A).
The table below shows where to apply (checked in November 2026; the monetary limit is reset every year).
| Dispute | Where to apply | Precondition |
|---|---|---|
| Worth less than 186,000 TL (2026) | Consumer arbitration committee | No mediation required |
| Refund or rent loss, above the limit | Consumer court | Application to a mediator first |
| Claims concerning rights in rem over the property, such as annulment of title and registration | Consumer court | No mediation required |
Whether mediation ends in agreement or not, the mediation fee falling to the consumer is covered from the budget of the Ministry of Justice, within the limit in the law.
Can a buyer living abroad pursue a delivery dispute without coming to Turkey?
Yes, a buyer living abroad can pursue a delivery dispute without coming to Turkey, through a power of attorney given to his or her lawyer. A power of attorney given from abroad is subject to different form rules depending on the country where it is drawn up. Powers such as settling and applying to a mediator must also be expressly written in the power of attorney.
A consumer lawsuit can be filed with the consumer court at the consumer's domicile as well as with the court of general jurisdiction. For a buyer with no domicile in Turkey, the place where the lawsuit is filed is determined by the seller's domicile and the place of performance of the contract. In lawsuits for annulment of title and registration, the court where the property is located has exclusive jurisdiction.
In the file decided in 2026, the seller had also argued that the buyer had to deposit security because he was a foreigner. This defence did not change the outcome of the case. The case of the buyer living in the US was heard through the claimant's lawyer; the notice of withdrawal and mediation can also be handled by a representative.
Which documents matter in a dispute over a home that has not been delivered?
In a dispute over a home that has not been delivered, what is decisive is not the number of documents but the documents showing the delivery date, the payment and the form of the contract. In a withdrawal claim, payment records stand out; for a buyer who chooses to wait, rent and delivery correspondence.
- On the contract: the notarial promise to sell or the contract signed at the office, the pre-contract information form, additional protocols.
- On payment: bank receipts, foreign currency transfer records, promissory notes, the linked credit agreement.
- On delivery and delay: the developer's correspondence, the invitation to take delivery, formal notices, photographs showing the state of construction.
- On security and the title deed: the building completion insurance policy, the letter of guarantee, the land registry record of the construction servitude.
Not all of these documents are needed in every file. The security policy may be decisive in a project in concordat proceedings, while in a project with fewer than 30 homes it may not exist at all. Which document supports which claim is determined by reviewing the file.
Conclusion: for a home that has not been delivered, the type of contract and the delivery date must be established first
When an off-plan home is not delivered, the buyer's rights are broad, but not every right gives the same result. A buyer who waits for the home claims rent loss or the penalty; a buyer who withdraws gets the price back without deductions; and a buyer who gives up on performance can claim the market value of the home.
The choice is determined by whether the contract was made before a notary, the delivery date, the currency of payment and the developer's financial situation. For payment in foreign currency, the outcome is also affected by the date of the contract, the buyer's citizenship and whether he or she is resident in Turkey.
If the developer has entered concordat, building completion insurance and security come to the fore. If the contract was signed before 1 October 2022, the statutory maximum is, as a rule, 36 months; this date is also part of the calculation.
Once a route has been chosen, it is not always possible to go back; a buyer who withdraws from the contract can no longer claim delivery of the home and rent loss, and a buyer who takes delivery of the home without reservation may lose the penalty. The route should therefore be chosen after the contract and payment records have been reviewed.
How can Legal Istanbul help when an off-plan home is not delivered?
In the files of foreign buyers of off-plan homes, Legal Istanbul reviews the promise-to-sell agreement, the delivery date, the extension and penalty clauses and the payment records. This review shows whether waiting for the home and claiming compensation or withdrawing from the contract is more suitable.
The firm prepares the notice of withdrawal and formal notices and conducts the mandatory mediation process and the lawsuit in the consumer court. Where necessary, it follows claims under building completion insurance or security and the notification of claims in concordat proceedings. If you have the promise-to-sell agreement and the payment receipts, you can contact Legal Istanbul to have the undelivered home assessed.
Discuss your late delivery file with a lawyer from the Legal Istanbul team.
The promise-to-sell agreement, payment receipts, correspondence with the developer, any formal notice and security or insurance documents help with the initial assessment. State the delivery date in the contract and whether the contract was made before a notary in your first message.
Delivery of off-plan homes: legal basis and official sources
- Legislation Information SystemConsumer Protection Law No. 6502 — pre-paid housing, form, security, 48 months, withdrawal and 180 days, arbitration committee, mediation (Art. 3, 35, 40-45, 68, 73, 73/A); as of November 2026
- Official GazetteLaw No. 7392 Amending the Consumer Protection Law and the Condominium Law — 48-month maximum, transitional provision and entry into force on 1 October 2022 (Art. 6, 17, 19)
- Legislation Information SystemTurkish Code of Obligations No. 6098 — default, optional rights, foreign currency debts and penalty clauses (Art. 97, 99, 117, 125, 179, 180)
- Legislation Information SystemEnforcement and Bankruptcy Law No. 2004 — consequences of the definitive moratorium in concordat for creditors (Art. 294)
- Wikimedia CommonsPhoto of unfinished homes in Kuşadası: Roy Egloff, Wikimedia Commons — used under the CC BY-SA 4.0 licence, cropped
Frequently asked questions
Does Turkish law give the developer a 6-month penalty-free grace period for delay?
No, in a pre-paid housing sale, the law gives the developer no penalty-free 6-month grace period for delay. The developer must deliver on the delivery date in the contract and within 48 months at the latest (as a rule, 36 months for contracts concluded before 1 October 2022). The 180 days are not a grace period for delay but the period within which the money must be refunded after the buyer withdraws from the contract. If the contract also states an extension, that clause is examined separately.
Can I stop paying the remaining instalments because delivery is late?
Stopping the remaining instalments on your own is not safe. If the contract provides that the instalments are to be paid before delivery, a buyer who stops paying may himself or herself be considered in default. This can give the seller a defence of withdrawal from the contract and compensation. Before stopping payment, it is safer to choose the route of withdrawal or a formal notice and to notify the reasons through a notary.
If the construction servitude title deed has been transferred to my name, is the home considered delivered?
Registration of the construction servitude in the buyer's name is not, on its own, delivery. The law requires that, together with registration of the construction servitude in the land registry, possession, that is, actual use of the home, is also transferred. For a buyer who has received the title deed but not the use of the home, the delivery obligation continues; for the purposes of the statutory maximum, the delay continues. The land registry record, however, strengthens the buyer's position if the developer goes bankrupt or enters concordat.
If a home I bought with a mortgage loan is not delivered, is the bank also liable?
Yes, if the loan is linked credit, the bank is jointly and severally liable with the seller. Linked credit is a loan given only for the purchase of that home and forming an economic unit with the sale. The bank's liability is limited to the amount of credit used. If the home has not been delivered, this liability lasts 1 year from the delivery date in the contract; this time limit should therefore not be missed.
Can I also claim rent loss after withdrawing from the contract?
No, a buyer who withdraws from the contract cannot claim rent loss as if the contract were continuing. In addition to the refund of the price, a buyer who withdraws can claim reliance damages, that is, the damage he or she would not have suffered if the contract had not been made. Notary costs and contract expenses are typical examples of this damage. In a 2023 decision, the Court of Cassation upheld a decision ordering the refund of reliance damages calculated in dollars.
How is a notice of withdrawal from the contract given in a pre-paid housing sale?
In a pre-paid housing sale, sending the notice of withdrawal to the seller through a notary is the safest route. A notice through a notary shows conclusively on which day the notice reached the seller. This date is important because the statutory refund period starts from the day the notice reaches the seller. Stating the intention to withdraw clearly in the notice prevents disputes that may arise later.
What happens if the developer does not refund the money within 180 days?
If the developer does not refund within 180 days, the buyer can file a lawsuit for refund of the price together with interest. If the value is above the arbitration committee limit, a mediator must be applied to first. If the price was validly paid in foreign currency, the refund can be claimed in the same currency with the interest applied to deposits in that currency. At this stage, too, the seller cannot deduct withdrawal compensation.
Is it necessary to record an objection when taking delivery of a home delivered late?
Yes, it is important to record an objection when taking delivery of a home that arrives late. If a penalty for late delivery was agreed, a buyer who accepts the home without reservation may lose the right to claim this penalty. The delivery report should state that the right to compensation for the delay is reserved. This entry preserves the ability to claim the penalty after delivery; it should therefore be made when the report is signed.
Are the 14-day right of withdrawal and the 24-month right to withdraw in pre-paid housing used when delivery is delayed?
No, these two rights are not specific to delayed delivery. The 14-day right of withdrawal is for the first days after the contract is concluded. For withdrawal without reason within 24 months, the seller can claim compensation of 2 to 8 percent depending on the period. When delivery is delayed, the buyer withdraws on the basis of the seller's default and bears no deduction at all.
Can a price paid in Turkish lira be recovered adjusted for inflation?
Yes, under a promise to sell made before a notary, a buyer who withdraws because of the developer's default can claim the updated value of the price paid in Turkish lira if he or she expressly makes this claim. In 2025 decisions, the Court of Cassation based this claim on the principle of corrective justice and the rules of unjust enrichment. The adjustment is not made automatically; the court is bound by the buyer's claim.
This article is for general information and is not a substitute for legal advice. Each file must be assessed separately on the basis of its own decisions and records.

